Related citation: | LI Yong-mei,SHI Yan-sheng,ZHANG Yi-gang,ZHANG Li,LIU Jia,WU Jin-zhi.Test research and computer simulation analysis of construction state during form finding for suspen-dome system[J].Journal of Harbin Institute Of Technology(New Series),2010,17(5):690-696.DOI:10.11916/j.issn.1005-9113.2010.05.017. |
|
Author Name | Affiliation | LI Yong-mei | Beijing Key Lab of Earthquake Engineering and Structural Retrofit,Beijing University of Technology,Beijing 100124,China Key Laboratory of Urban Security and Disaster Engineering,Ministry of Education,Beijing University of Technology,Beijing 100124,China | SHI Yan-sheng | Beijing Key Lab of Earthquake Engineering and Structural Retrofit,Beijing University of Technology,Beijing 100124,China | ZHANG Yi-gang | Beijing Key Lab of Earthquake Engineering and Structural Retrofit,Beijing University of Technology,Beijing 100124,China | ZHANG Li | Beijing Key Lab of Earthquake Engineering and Structural Retrofit,Beijing University of Technology,Beijing 100124,China | LIU Jia | Beijing Key Lab of Earthquake Engineering and Structural Retrofit,Beijing University of Technology,Beijing 100124,China | WU Jin-zhi | Beijing Key Lab of Earthquake Engineering and Structural Retrofit,Beijing University of Technology,Beijing 100124,China |
|
Abstract: |
A novel construction method without scaffold work called as assembly-prestressing form finding loop by loop is presented.Based on the theory of finite displacement,the cycle-forward analysis method is presented for its construction calculation,which adopts the finite element method of generalized geometric nonlinearity combined with the application in the real construction process.By means of the combination of the forward analysis according to real construction sequence and the cycle iteration according to the initial strain increment method of cable force adjustment,the influence of the structural geometric nonlinearity and the loss of prestress are taken into account due to prestressing of tendons in turn and so on.If the initial cable forces derived from the method were used for construction,expected cable forces and shape could be assured easily.Simulation analysis achieved real-time tracking and controlling of the construction status.Finally,according to the procedure and parameters in simulating,a model experimental research on the stage of form finding(namely prestressing)was carried out for suspen-dome structure.The feasibility on the assembly-prestressing form finding method loop by loop was testified.The cycle-forward analysis method was established and numerical simulation was performed,and the results show that it was useful for the design and the construction of similar suspen-dome structure. |
Key words: suspen-dome assembly-prestressing form finding loop by loop cycle-forward analysis the increment of initial strain form finding test |
DOI:10.11916/j.issn.1005-9113.2010.05.017 |
Clc Number:TU399 |
Fund: |