引用本文: | 陈云钢,刘家彬,郭正兴,张建玺.装配式剪力墙水平拼缝钢筋浆锚搭接抗震性能试验[J].哈尔滨工业大学学报,2013,45(6):83.DOI:10.11918/j.issn.0367-6234.2013.06.015 |
| CHEN Yungang,LIU Jiabin,GUO Zhengxing,ZHANG Jianxi.Test on seismic performance of precast shear wall with reinforcements grouted in holes and spliced indirectly in horizontal connections[J].Journal of Harbin Institute of Technology,2013,45(6):83.DOI:10.11918/j.issn.0367-6234.2013.06.015 |
|
摘要: |
为综合评价水平拼缝采用竖向钢筋浆锚搭接的装配式混凝土剪力墙抗震性能,采用2个装配式和1个现浇的足尺试件进行低周反复荷载试验.试验结果表明:对于破坏形态,装配式混凝土剪力墙内墙试件与现浇试件基本相同,装配式混凝土剪力墙外墙试件与现浇试件有区别;各试件的滞回曲线均较饱满,骨架曲线走势基本一致,耗能能力接近;各试件极限位移角1/56~1/49,位移延性系数均为4;装配式混凝土剪力墙试件较现浇试件初期刚度有所降低,外墙试件水平拼缝上移后,承载能力有所提高. |
关键词: 装配式剪力墙 水平拼缝 浆锚搭接 抗震性能 |
DOI:10.11918/j.issn.0367-6234.2013.06.015 |
分类号: |
基金项目:“十二五”国家科技支撑计划项目(2011BAJ10B03):装配式建筑混凝土剪力墙结构关键技术研究. |
|
Test on seismic performance of precast shear wall with reinforcements grouted in holes and spliced indirectly in horizontal connections |
CHEN Yungang1,2, LIU Jiabin1, GUO Zhengxing1, ZHANG Jianxi1
|
(1. School of Civil Engineering, Southeast University, 210096 Nanjing, China; 2. School of Civil Engineering and Architecture, Anhui University of Technology,243002 Ma’anshan, Anhui,China)
|
Abstract: |
To comprehensively evaluate the seismic performance of precast concrete shear wall with vertical reinforcements grouted in holes and spliced indirectly in horizontal connections, two fabricated and a cast-in-place concrete shear wall with full scale specimens were tested under low cyclic loading. The test results show that the concrete interior shear wall specimens (JN) is basically the same as the cast-in-place specimen (XJ) in failure modes, but the concrete exterior shear wall specimen wall (JW) is different with the XJ. The hysteresis curve of the specimen is full, the trend of the skeleton curve is basically the same and the capacity of the energy dissipation is close. The ultimate displacement angle of each specimen is 1/56-1/49 and the displacement ductility factor are 4. The initial stiffness of JW, JN are lower than the XJ, and the force behavior is improved in exterior wall specimens (JW) with the setting position of horizontal connections moved up. |
Key words: precast shear wall horizontal connections grouted and splicing seismic performance
|